How do I start a solar farm in India?
Checked 24 November 2026
Find the buyer for the power first, because a solar farm is a long power purchase agreement with a plant attached. PM-KUSUM, which let farmers sell up to 2 MW to the DISCOM, now only finishes projects whose agreements were signed by the end of 2025, so a new farm needs a buyer of its own.
By case
-
If you signed a PM-KUSUM agreement before the cut-off
Finish and commission the plant before the extended deadline.
Only those projects got the extension.
-
If you are starting now
Sign a power purchase agreement with a large consumer or win a DISCOM tender before you buy land or equipment.
A farm without a signed buyer cannot be financed.
-
If you sell to a DISCOM
Expect the tariff the state regulator sets, not one you negotiate.
Under PM-KUSUM the tariff was determined by the state regulator.
-
If you want a second income from the plant
Check whether it qualifies under BEE's methodology for grid-connected renewable electricity.
Qualifying projects can earn carbon certificates under the offset mechanism.
The steps5 steps
-
Line up the buyer and sign the power purchase agreement.
-
Secure the land close to a substation with capacity to take your power.
-
Apply for the grid connection and the approvals your state requires.
-
Raise the loan against the signed agreement, build and commission the plant.
-
If it qualifies, register it under BEE's offset mechanism.
The figuresEach with where it was read
- Largest plant under PM-KUSUM Component A 2 MW
- Component A capacity sanctioned and installed, as of 31 October 2026 5,894 MW and 1,530.51 MW
- Date of MNRE's order on the extension 25 May 2026
- PPAs eligible for the extension, signed by 31 December 2025
- Extended completion deadline 31 March 2027
- Incentive to a DISCOM buying Component A power 40 paise a kWh or Rs 6.60 lakh a MW a year, for five years
What goes wrong
Buying land or modules before a buyer has signed for the power.
Choosing land far from a substation that has spare capacity.
Planning on PM-KUSUM for a project that had no agreement by the end of 2025.
Go deeper5 sources
-
National Portal for PM-KUSUM (MNRE)
Ministry of New and Renewable Energy · pmkusum.mnre.gov.in · Tool · India
The scheme's own portal, with what each component offers, a live achievement dashboard and the ministry's latest orders.
-
Extension of timeline for completion of projects under PM-KUSUM, clarification (MNRE, 25 May 2026)
Ministry of New and Renewable Energy · apipmk.mnre.gov.in · Official · India
The ministry's order on which PM-KUSUM projects may still be completed and by when.
-
Financial and technical support to promote new and renewable energy (PIB)
Press Information Bureau · pib.gov.in · Official · India
The government's summary of what each renewable scheme pays, including PM Surya Ghar's subsidy table and PM-KUSUM's three components.
-
Methodologies and Tools under Offset Mechanism (BEE)
Bureau of Energy Efficiency · beeindia.gov.in · Official · India
The current list of project types that can earn Indian carbon certificates, each with its methodology document.
-
Detailed Procedure for Offset Mechanism under CCTS (BEE)
Bureau of Energy Efficiency · beeindia.gov.in · Official · India
The rulebook for earning certificates from a project: the seven-step cycle from account to issuance, the crediting periods and the fee schedule.